Investment activity
2 quarter
Quarterly amount of investments in 2022 – 2026
Graph
Change*, %
* – change is calculated on the basis of the indicators presented in the table and rounded to the nearest tenth
|
Начальное изменение |
2Q '22 |
2Q '23 |
2Q '24 |
2Q '25 |
2Q '26 |
|
CAPEX without VAT, million RUR |
-7,7 |
2 123,2 |
3 380,9 |
3 457,9 |
4 050,6 |
4 673,1 |
|
- Grid connection |
24,1 |
1 139,7 |
2 329,4 |
2 413,3 |
2 711,8 |
2 585,7 |
|
- New construction, million RUR |
-84,4 |
19,0 |
16,6 |
35,8 |
41,2 |
593,5 |
|
- Retrofitting and reconstruction, million RUR |
-44,9 |
629,7 |
705,9 |
642,5 |
1 054,5 |
1 141,1 |
|
- Other, million RUR |
183,2 |
334,8 |
329,0 |
366,3 |
243,1 |
352,8 |
|
Fixed assets commissioned without VAT, million RUR |
-18,8 |
2 219,5 |
2 564,7 |
3 407,2 |
5 449,5 |
4 297,6 |
|
Financing with VAT, million RUR |
-19,0 |
2 575,4 |
4 554,7 |
5 172,3 |
6 433,2 |
6 569,7 |
|
Сapacity commissioned, km |
-41,4 |
310,9 |
574,1 |
668,8 |
610,1 |
407,7 |
|
Сapacity commissioned, MVA |
48,7 |
68,7 |
54,8 |
89,1 |
183,4 |
165,3 |