Investment activity
1 quarter
Quarterly amount of investments in 2022 – 2026
Graph
Change*, %
* – change is calculated on the basis of the indicators presented in the table and rounded to the nearest tenth
|
Начальное изменение |
1Q '22 |
1Q '23 |
1Q '24 |
1Q '25 |
1Q '26 |
|
CAPEX without VAT, million RUR |
-7,4 |
1 724,3 |
2 576,7 |
2 379,0 |
4 307,1 |
3 146,8 |
|
- Grid connection |
12,5 |
1 036,5 |
1 679,9 |
1 669,5 |
2 603,7 |
1 815,8 |
|
- New construction, million RUR |
-86,1 |
8,2 |
71,5 |
67,4 |
42,2 |
35,3 |
|
- Retrofitting and reconstruction, million RUR |
-26,9 |
566,6 |
558,0 |
443,9 |
969,5 |
923,1 |
|
- Other, million RUR |
5,4 |
113,0 |
267,3 |
198,2 |
691,7 |
372,6 |
|
Fixed assets commissioned without VAT, million RUR |
-41,0 |
1 245,1 |
2 325,7 |
1 938,8 |
3 066,8 |
2 184,1 |
|
Financing with VAT, million RUR |
17,5 |
4 516,6 |
4 607,2 |
5 093,8 |
7 612,4 |
8 396,7 |
|
Сapacity commissioned, km |
-30,4 |
318,9 |
553,3 |
441,3 |
830,5 |
370,5 |
|
Сapacity commissioned, MVA |
-51,4 |
22,8 |
50,3 |
167,5 |
153,1 |
39,0 |