Site colours:
Zoom:

Investment activity

Annual indicators

Annual amount of investments in 2017-2021

Graph
Начальное изменение 2017 2018 2019 2020 2021
CAPEX without VAT, billion RUR, including: 3.1 11,8 12,2 11,8 13,8 14,1
- Grid connection -17.7 5,0 4,9 4,5 5,0 5,2
- New construction, billion RUR 150.0 0,7 0,3 0,5 0,3 1,0
- Retrofitting and reconstruction, billion RUR 5.4 5,8 6,9 6,8 8,3 7,8
- Others, billion RUR 0.0 0,2 0,1 0,1 0,1 0,1
Fixed assets commissioned without VAT, billion RUR 5.5 11,8 12,7 11,2 12,2 15,4
Financing with VAT, billion RUR -3.9 14,2 14,5 13,6 14,0 16,9
Сapacity commissioned, km 0.9 4075,0 3598,0 3350,9 2098,3 2700,8
Сapacity commissioned, MVA -25.3 560,0 376,0 425,6 374,3 386,0

Main indicators of the Investment program 2022-20261


2022 2023 2024 2025 2026
CAPEX without VAT, billion RUR 12,5 18,5 19,5 14,2 12,7
Fixed assets commissioned without VAT, billion RUR 13,7 18,7 19,4 14,8 13,0
Financing with VAT, billion RUR 15,4 22,0 24,3 17,2 17,2
Сapacity commissioned, km 2 310 2 270 2 629 2 509 2 392
Сapacity commissioned, MVA 282 286 204 429 549
1 - according to Order of the Ministry of Energy from 22.12.2021 №23

The Investment program structure (CAPEX) (without VAT) for 2022-2026 broken down by the branches1


billion RUR 2022 2023 2024 2025 2026
Belgorodenergo 2,5 3,3 3,0 2,5 2,1
Bryanskenergo 0,7 1,2 1,2 0,8 0,9
Voronezhenergo 2,3 3,2 3,9 2,8 2,0
Kostromaenergo 1,0 1,3 1,1 1,1 1,1
Kurskenergo 0,7 1,1 1,0 1,1 1,0
Lipetskenergo 1,6 1,6 2,2 1,4 1,1
Orelenergo 0,4 0,7 0,8 0,7 0,7
Smolenskenergo 1,0 1,6 1,7 1,1 0,9
Tambovenergo 0,6 1,4 1,4 0,8 0,8
Tverenergo 0,4 1,8 2,0 0,5 0,5
Yarenergo 1,3 1,4 1,4 1,4 1,5
Total 12,5 18,5 19,5 14,2 12,7
1 - according to Order of the Ministry of Energy from 22.12.2021 №23

Priority investment projects completed in 2021


Priority investment projects completed in 2021:

Project name,
location of the facility

Goals and objectives of the project

Design capacity

(MVA, km)

Work within the project

Implementation period

Funding, thous. RUB

planned 

performed

Construction of 110/10 kV Sputnik Substation for grid connection of LLC Vybor contract №41199851 of 28.03.16; LLC Remstroy №41210590 of 16.09.16 (over 670 kW; transformer capacity 80 MVA). city of Voronezh

The project envisages the commissioning of new capacities. the expansion of the electricity sales market.. implementation of a number of large grid connection contracts. and also increase of reliability of power supply in the northern part of the city of Voronezh. Implementation of the concept “Digital Transformation”

80 MVA

Construction of a two transformer Substation 110 kV with transformers 2х40 MVA with the separation of their power to the load voltage of 10 kV

2015-2020

1 076 201

913 095

Priority investment projects1


Project name,
location of the facility

Goals and objectives of the project

Design capacity
(MVA, km)

Work within the project

Implementation period, financing % at the reporting date

Funding, thous. RUB

planned

performed

Reconstruction of 110/10 kV South Substation with replacement of power transformers of 2х40 MVA for 2х32 and 2х6.3 MVA, installation of a rapidly erected building: indoor Switchgear-6kV, indoor Switchgear-10kV, a substation control building with relay protection and automation panels, remote control and digital communications channel (transformer capacity 76.6 MVA), Belgorod region

The project provides for the renovation of basic production assets, the elimination of the power deficit of the Power Centre, and the improvement of the reliability of electricity supply to customers, creating opportunities to connect new customersers

76.6 MVA

Reconstruction of SS-110 kV with installation of two additional transformers 2х6.3 MVA and replacement of existing 2х40MVA for 2х32 MVA

2012-2025
4%

654 817

29 359

Reconstruction of 110/35/10 kV Korocha Substation with the transfer of SS to a new site. Instead of three transformers TDTN-16000/110/35/10 two transformers TDTN-25000/110/35/10 are installed, equipment of outdoor Switchgear 110 kV under the circuit №110-13, outdoor Switchgear 35 kV under the circuit №35-9, indoor Switchgear-10 kV in a rapidly erected building (power increase by 2 MVA), Belgorod region

The project provides for the renovation of basic production assets, the elimination of the power deficit of the Power Centre, and the improvement of the reliability of electricity supply to customers

50 MVA

Reconstruction of a two transformer Substation 110/35/10 kV with installation of transformers 2х25 MVA 

2016-2025
13%

1 027 681

135 925

Reconstruction of 110 kV Mayskaya Substation with replacement of transformers 2хTRDN-40000/110/10 for 2хTDTN-40000/110/35/10 and installation of 35 kV bays (8 pieces) (transformer capacity 80 MVA), Belgorod region

The project provides for the renovation of basic production assets, the elimination of the power deficit of the Power Centre, and the improvement of the reliability of electricity supply to customers

80 MVA

Reconstruction of a two transformer Substation 110/10 kV with installation of transformers 2х40 MVA and installation of 35 kV bays

2016-2025
2%

322 566

6 202

1 In accordance with the Investment Program, approved by the Ministry of Energy on 22.12.2021 №23