Site colours:
Zoom:

Investment activity

Annual indicators

Annual amount of investments in 2015-2019

Graph
Начальное изменение 2015 2016 2017 2018 2019
CAPEX without VAT, billion RUR, including: 3.1 13.4 11.8 12.2 11.8 13.0
- Grid connection -17.7 6.5 5.0 4.9 4.5 7.9
- New construction, billion RUR 150.0 3.0 0.7 0.3 0.5 1.2
- Retrofitting and reconstruction, billion RUR 5.4 3.9 5.8 6.9 6.8 3.7
- Others, billion RUR 0.0 0.1 0.2 0.1 0.1 0.1
Fixed assets commissioned without VAT, billion RUR 5.5 13.5 11.8 12.7 11.2 12.8
Financing with VAT, billion RUR -3.9 14.6 14.2 14.5 13.6 15.2
Сapacity commissioned, km 0.9 4 827.0 4 075.0 3 598.0 3 350.9 4 785.0
Сapacity commissioned, MVA -25.3 917.0 560.0 376.0 425,6 1 228.0

Main indicators of the Investment program 2020-20241


2020 2021 2022 2023 2024
CAPEX without VAT, billion RUR 13.4 13.0 12.6 12.4 12.0
Fixed assets commissioned without VAT, billion RUR 16.6 14.9 14.8 14.8 14.5
Financing with VAT, billion RUR 14.6 12.9 12.6 13.2 12.6
Сapacity commissioned, km 3 253 2 600 2 700 3 243 3 794
Сapacity commissioned, MVA 506 396 289 266 213
1 - according to Order of the Ministry of Energy from 26.12.2019 № 35@

The Investment program structure (CAPEX) (without VAT) for 2020-2024 broken down by the branches1


billion RUR 2020 2021 2022 2023 2024
Belgorodenergo 2.2 2.2 2.1 2.1 1.4
Bryanskenergo 0.6 0.8 1.0 0.7 0.7
Voronezhenergo 3.0 2.6 2.8 2.9 3.4
Kostromaenergo 0.9 1.0 0.9 1.0 1.0
Kurskenergo 1.0 1.4 0.9 0.9 0.9
Lipetskenergo 1.1 1.4 1.3 1.7 1.1
Orelenergo 0.3 0.4 0.4 0.4 0.4
Smolenskenergo 1.0 0.9 0.9 0.8 1.3
Tambovenergo 0.6 0.6 0.7 0.5 0.7
Tverenergo 1.3 0.3 0.1 0.2 0.1
Yarenergo 1.2 1.4 1.5 1.3 1.1
Total 13.4 13.0 12.6 12.4 12.0
1 - according to Order of the Ministry of Energy from 26.12.2019 № 35@

The Investment program structure (Financing) (with VAT) for 2020-2024 broken down by the branches1


billion RUR 2018 2019 2020 2021 2022
Belgorodenergo 3.0 2.1 2.0 2.2 1.3
Bryanskenergo 0.8 0.8 1.0 0.7 0.8
Voronezhenergo 3.2 2.7 2.4 3.4 3.5
Kostromaenergo 0.6 0.7 1.4 0,9 1.2
Kurskenergo 0.7 1.7 0.9 0.8 1.0
Lipetskenergo 1.4 1.5 1.1 1.7 1.1
Orelenergo 0.3 0.4 0.4 0.4 0.5
Smolenskenergo 1.1 0.9 0.9 0.8 1.3
Tambovenergo 0.7 0.4 0.9 0.5 0.7
Tverenergo 1.5 0.4 0.1 0.2 0.1
Yarenergo 1.2 1.4 1.5 1.6 1.1
Total 14.6 12.9 12.6 13.2 12.6
1 - according to Order of the Ministry of Energy from 26.12.2019 № 35@

Priority investment projects completed in 2019


Priority investment projects completed in 2019:

Project name, location of the facility

Goals and objectives of the project

Design capacity

(MVA, km)

Work within the project

Implementation period

Funding, thous. RUB

planned 

performed

Construction of Cable line 110 kV 220 kV Buturlinovka Substation - 110 kV Buturlinovka Substation-2 circuit 1, 2 (length of 0,97 km), Voronezh region.

Implementation of the power delivery scheme of Novovoronezh NPP-2

0,97 km

Construction of a new 110 kV cable line, circuit 1, 2

2013-2019

35 469

37 473

Facilities of grid connection of LLC Miratorg

Grid connection of customers with capacity up to 15 kW NSiR BR-509 (construction of a 10 kV overhead line 5m, construction of a transformer substation, construction of a 0.4 kV overhead line 5 m Grid connection contract 41769766 of 19.02.2019)

Implementation of grid connection contracts.

0,015 MVA

Construction of a 10 kV overhead line, a 0.4 kV overhead line and a 10/0.4 kV pole-mounted transformer

2019-2019

440

392

Grid connection of customers with capacity up to 15 kW NSiR BR-509 (construction of a 0.4 kV overhead line with the length of 140 m Grid connection contract 41767411 of 19.02.2019)

Implementation of grid connection contracts.

0,015 MVA

Construction of a 0.4 kV overhead line

2019-2019

420

118

Grid connection of customers with capacity up to 15 kW NSiR BR-509 (construction of a 10 kV overhead line 300m, construction of a transformer substation, construction of a 0.4 kV overhead line 5 m Grid connection contract 41768534 of 19.02.2019)

Implementation of grid connection contracts.

0,015 MVA

Construction of a 10 kV overhead line, a 0.4 kV overhead line and a 10/0.4 kV pole-mounted transformer

2019-2019

880

649

Grid connection of customers with capacity up to 15 kW NSiR BR-509 (construction of a 0.4 kV overhead line with the length of 70m Grid connection contract 41771732 of 19.02.2019), TPiR BR-510 (replacement of a transformer in a package transformer substation № 197. Grid connection contract 41771732 of 19.02.2019)

Implementation of grid connection contracts.

0,015 MVA

Construction of a 0.4 kV overhead line and installation of a power transformer in a package transformer substation

2019-2019

220

144

Grid connection of customers with capacity up to 15 kW NSiR BR-509 (construction of a 0.4 kV overhead line with the length of 54 m Grid connection contract 41767403 of 19.02.2019)

Implementation of grid connection contracts.

0,015 MVA

Construction of a 0.4 kV overhead line

2019-2019

80

112

Grid connection of customers with capacity up to 15 kW NSiR BR-509 (construction of a 10 kV overhead line, construction of a transformer substation, construction of a 0.4 kV overhead line Grid connection contract 41768485 of 19.02.2019)

Implementation of grid connection contracts.

0,015 MVA

Construction of a 10 kV overhead line, a 0.4 kV overhead line and a 10/0.4 kV pole-mounted transformer

2019-2019

530

428

Grid connection of customers with capacity up to 15 kW NSiR BR-509 (construction of a 0.4 kV overhead line with the length of 175m Grid connection contract 41770075 of 19.02.2019), TPiR BR-510 (replacement of a transformer in a transformer substation 5079. Grid connection contract 41770075 of 19.02.2019)

Implementation of grid connection contracts.

0,015 MVA

Construction of a 0.4 kV overhead line and installation of a power transformer in a package transformer substation

2019-2019

370

266

Construction of a 10 kV overhead line f.07 35/10 kV Molotychi Substation for grid connection of LLC Miratorg-Kursk contract №41626344 of 17.05.18 (up to 670 kW; the length of 4,5 km) Implementation of grid connection contracts.

4,55 km

Construction of a 10 kV overhead line

2019-2019

6 959

6 874

Upgrade of 35/10 kV Molotychi Substation with installation of an additional 10 kV bay for grid connection of LLC Miratorg-Kursk contract №41626344 of 17.05.18 (up to 670 kW) Implementation of grid connection contracts.

0,37 MVA

Installation of a 10 kV bay in indoor Switchgear-10 kV Substation 35/10 kV

2019-2019

1 678

1 679

Construction of a 10 kV overhead line from a new bay of 110/10 kV ARZ Substation to the border of the Applicant’s balance participation with installation of disconnectors (4 pcs) for grid connection of Miratorg-Kursk LLC №41638346 of 10.09.18 (over 670 kW; the length of 8,86 km). Construction of a 10 kV cable line - an intermediate cable of the 10 kV overhead line being constructed from 110/10 kV ARZ Substation to the border of the Applicant’s balance participation of Miratorg-Kursk LLC №41638346 of 10.09.18 (over 670 kW; the length of 1,093 km, including horizontal directional drilling - 0,403 km) Implementation of grid connection contracts.

9,95 km

Construction of a 10 kV overhead line

2019-2019

15 239

14 076

Upgrade of 110/10 kV ARZ Substation with installation of an additional 10 kV bay for grid connection of LLC Miratorg-Kursk, contract №41638346 of 10.09.18 (over 670 kW) Implementation of grid connection contracts.

0,74 MVA

Installation of a 10 kV bay in indoor Switchgear-10 kV Substation 35/10 kV

2019-2019

1 788

1 799