IDGC of Centre for nine months put into operation more than 2,000 kilometres of power lines and more than 240 MVA of capacity

1 November 2017

IDGC of Centre summed up the results of the investment program implementation for 9 months of 2017. During this period the company commissioned 242 MVA of capacity, which is 102 MVA higher than the planned value, and 2,219 km of power lines, exceeding the plan by 449 kilometres.

The volume of the program financing amounted to 8.9 billion rubles (including VAT), which is 103% of the planned volume. In particular, 4.3 billion rubles was allocated for technical re-equipment and reconstruction, 4.6 billion rubles for construction of new and expansion of existing facilities, which also corresponds to the planned indicators.

In total, this year IDGC of Centre plans to put into operation more than 600 MVA of capacity and more than 3,000 kilometres of power lines. To implement the investment program of 2017 it is planned to spend 15.312 billion rubles. About 58% of the investments planned by the document will go for technical re-equipment and reconstruction, 42% - for new construction and expansion of power grid infrastructure.

Back to the list