Voronezhenergo to spend more than 590 million rubles on the implementation of the repair program in 2020

24.01.2020

The branch “Rosseti Centre Voronezhenergo” has started implementing its maintenance and repair program. In 2020, power engineers will have to repair over 430 transformer substations of 10-0.4 kV and almost 2,000 kilometres of overhead power lines of various voltage levels. More than 590 million rubles will be allocated for these purposes.

Overhaul of power lines is planned on about 70 lines of 35-110 kV. The power engineers will perform the largest amount of work on the cable-overhead line of 110 kV CHPP-1 - DSK No. 5, as well as on the overhead lines of 110 kV Novovoronezh NPP - Bobrov, Conductor 110 kV Bobrov-Buturlinovka-2 No. 1 and No. 2, Conductor 110 kV Voronezh-Kirovskaya No. 45 and No. 46.

Equipment repair is also planned at more than 60 substations of 35 and 110 kV. In particular, Voronezhenergo’s specialists will repair equipment at 110 kV substations No. 21 “Vostochnaya”, No. 16 “Yugo-Zapadnaya”, No. 28 “Teplichnaya” and No. 32 in the city of Voronezh, which will ensure reliable and high-quality power supply to such large industrial and social significant consumers, as Mechanical Plant, KBHA, Ceramic Plant, JSC Voronezh Gorelektroset, Vodokanal,

Much attention will be still paid to clearing routes of power lines from trees and shrubs, which is carried out in order to prevent occurrence of emergency situations. This year, Voronezhenergo’s specialists will have to clear more than 1,450 hectares of routes of power lines. About 43 million rubles will be allocated for these purposes.