The branch “Rosseti Centre Smolenskenergo” completed the repair of the 110/35/10 kV “Temkino” substation, the main supply centre of the settlement of the same name, which is the administrative centre of Temkinsky district of the Smolensk region.

The branch’s specialists performed overhaul of disconnectors and circuit breakers, as well as the current repair of two 110 kV power transformers with a total capacity of 20 MVA. “The work carried out will ensure reliable and uninterrupted power supply to residents of the settlement of Temkino. It is important that they were carried out without de-energizing consumers,” commented Vitaliy Golubkov, the head of the analysis and production management department.