For six months Voronezhenergo completed 60% of the total repair program

05.08.2019

The branch “Rosseti Centre Voronezhenergo” summed up the results of the implementation of the repair program in the first half of 2019. All activities planned for the reporting period were completed in full and on time. From January to June, Voronezhenergo’s specialists repaired over 866.5 km of 0.4-110 kV overhead power lines, replaced about 17.1 thousand insulators and over 15.7 km of lightning protection cables. Equipment was repaired at 231 transformer substations. Over 936.4 hectares of routes along power lines were cleared from tree and shrub vegetation. 159.9 million rubles were allocated for the implementation of the repair program in the first half of the year.

In total, as part of the repair campaign of the current year, Voronezhenergo’s specialists will have to repair over 1,362.4 kilometres of 0.4-110 kV overhead power lines and 403 transformer substations. Overhaul of the equipment is also planned at 39 substations of the voltage levels of 35 and 110 kV. In order to prevent emergencies, it is planned to clear more than 1,402.2 hectares of routes along overhead power lines from trees and shrubs.

Implementation of Voronezhenergo’s repair program activities in a quality and timely manner allows the efficient functioning of the region’s electric grid complex, as well as trouble-free passage of the heating season. The power engineers plan to complete the main activities stipulated by the document by the end of September 2019.

Other News

Back to the list