The branch “Rosseti Centre Tambovenergo”* summed up the implementation of the repair program for five months of 2019. All activities scheduled from January to May were fully implemented.
52 transformer substations of 6-10 kV, 71 transformers of 10/0.4 kV and about 142 kilometres of 0.4-110 kV overhead lines were repaired. More than 180 hectares of routes along overhead lines were cleared from tree and shrub vegetation.
In total, in 2019, Tambovenergo plans to repair 723,126 kilometres of overhead lines and 157 transformer substations, clear more than 514 hectares of routes along overhead lines, repair equipment of 35-110 kV substations. The main part of the work will be completed by 1 October.