Voronezhenergo successfully implements the repair program - 2019

13.05.2019

IDGC of Centre - Voronezhenergo division summed up the results of the implementation of the repair program in 1Q 2019. All measures planned for the reporting period were completed in full and on time, which contributed to the trouble-free passage of the heating period of 2018-2019.

From January to March of this year, Voronezhenergo’s specialists repaired more than 170 km of overhead power lines of 0.4 -110 kV, replaced about 2 thousand insulators and over 15 km of overhead ground-wire cable. Repair of equipment was carried out at 45 transformer substations. To ensure reliable power supply to consumers, over 300 hectares of power lines of various voltage levels were also cleared from trees and shrubs. The cost of the implementation of the entire range of work on the repair program in 1Q 2019 amounted to 44.46 million rubles.

In total, within the framework of the repair campaign of the current year, Voronezhenergo’s specialists will have to repair more than 1,360 kilometres of 0.4-110 kV overhead power lines and 403 transformer substations. Equipment overhaul is also planned at 39 substations of 35 and 110 kV voltage levels. In order to prevent emergencies, it is planned to clear more than 1,400 hectares of routes along overhead power lines from trees and shrubs.

In total, in 2019 Voronezhenergo will spend more than 443 million rubles on the maintenance and repair program.

Other News

Back to the list