Kurskenergo summed up the work on grid connection for 2018

07.02.2019

IDGC of Centre - Kurskenergo division summed up the work on connection of customers to power grids for 2018.

Last year the branch received 2,585 applications for grid connection. 2,303 contracts were concluded, 2,072 contracts were executed, electricity supply was provided to 489 enterprises and 1,520 individual residential buildings. The total capacity of power installations connected to the grids was 49.3 MW.

As part of the contract execution, Kurskenergo’s experts constructed 112.4 km of 0.4–10 kV overhead lines and 8.5 km of 0.4–10 kV cable lines, installed 66 transformer points of 10/0.4 kV with a total capacity of 7,152 kVA.

The largest applicants, who were provided with the grid connection service, included agribusiness sector companies: “Agropromkomplektatsiya-Kursk” LLC and subsidiaries of Miratorg’s Group of Companies, “Fatezhskaya Lamb” LLC, “Pristenskaya Grain Company” LLC and “Vozrozhdenie” LLC.

In addition, Kurskenergo provided grid connection to a number of important social facilities in the region: the fire station in the village of Besedino, a kindergarten for 140 children in the urban-type settlement of Solntsevo, fitness centres in the city of Rylsk and the settlement of Glushkovo.

You can apply for connection to Kurskenergo’s grids by calling the toll-free direct line of power engineers at 8-800-50-50-115. Also, applications are accepted at the Customer Service Centres of the branch and points for work with customers, which are in each Distribution Zone of Kurskenergo.

On IDGC of Centre’s website at http://www.mrsk-1.ru/customers/fitting/, you can submit an online application for grid connection and other types of services of the branch, which allows you to significantly simplify the procedure and reduce the number of face-to-face visits to customer offices.