Tambovenergo fully implemented the repair program of 2018

30.01.2019

IDGC of Centre - Tambovenergo division summed up the implementation of the 2018 repair program. All of its activities were completed in full and on time, in a number of areas there was an advance of the schedule.

Power engineers repaired 133 transformer substations and 199 transformers of 10/0.4 kV, which is 3% ​​and 18% higher than the planned values, respectively, as well as 725 km of 0.4-110 kV overhead lines - 3.5% higher than the annual plan. 479.93 hectares of ROWs along overhead power lines were cleared from trees and shrubs.

“Full and timely implementation of the measures of the repair program allowed Tambovenergo to create the necessary conditions for uninterrupted operation of the power grid complex during the winter maximum load,” stressed Deputy General Director of IDGC of Centre - Tambovenergo division director Nikolay Bogomolov.