Tambovenergo for 9 months repaired over 725 kilometres of overhead lines

07.11.2018

IDGC of Centre - Tambovenergo division summed up the implementation of the repair program for nine months of 2018. All activities scheduled from January to September were fully performed.

132 transformer substations of 6-10 kV, 157 transformers of 10/0.4 kV and about 725 kilometres of 0.4-110 kV overhead lines were repaired. 479 hectares of ROWs along overhead lines were cleared from woody and shrubby vegetation.

"The implementation of the measures of the repair program will ensure the reliability of electricity supply to consumers in the Tambov region, improve the quality of power transmission, and prepare the regional power grid complex to operate through the autumn-winter period of 2018-2019," stressed Acting Deputy General Director of IDGC of Centre - Tambovenergo division director Nikolay Bogomolov.