Site colours:
Zoom:

Lipetskenergo’s specialists at the exercises in the Tver region perform their tasks ahead of schedule

16.10.2018

By 15 October, crews of IDGC of Centre - Lipetskenergo division cleared 149 hectares of ROWs in Kalininsky district with a plan of 133 hectares. Thus, 101 kilometres of power lines have been put in order. The branch’s chief engineer Vladimir Tikhonov personally inspected the progress of work.

“The management of the company is tasked with an integrated approach to work in the Tver region. Therefore, at the same time with clearing and expansion of 10 kV overhead lines, employees of our branch identify defects on the lines for further elimination. Additionally, specialists of the power line service inspect 35-110 kV overhead lines. They have already completed the inspection of 16 lines with a total length of 204 kilometres,” said Vladimir Tikhonov.

Currently, 113 Lipetsk power engineers are working in the Tver region.

Other News

Back to the list