Kurskenergo completed its main production plans in full for 9 months

01.11.2017

IDGC of Centre - Kurskenergo division summed up the results of production activity for 9 months of 2017. The enterprise fully implemented the plan for key areas of work. The volume of productive supply of electricity to the grid amounted to more than 3.5 billion kWh. The total effect of the energy saving and energy efficiency increase program was 2.09 million kWh.

In January-September, the energy company carried out a comprehensive overhaul of 23 substations of 35-110 kV, 416 transformer substations and distribution points. 473.8 km of 35-110 kV overhead lines and 2,112.4 km of 0.4-10 kV overhead lines were repaired.

1,449 grid connection contracts with a total connected capacity of 27.4 MW were performed. Among the significant connected facilities are a secondary school in Medvensky district, and the gas pipeline - the Nikolsky gas distribution station in Bolshesoldatsky district. The capacity of the new gas distribution station allowed to supply gas to more than 300 households in Bolshesoldatsky, Kurchatovsky and Lgovsky districts of the Kursk region.

Other News

Back to the list