Belgorodenergo fulfilled half the volume of the annual repair program

31.07.2017

In preparation for the failure-free operation through the autumn-winter period of 2017-2018 IDGC of Centre – Belgorodenergo division realized the planned volume of the repair program scheduled for the first half of the year, with overfulfillment of targets by 2.9% and monetary funds of more than 135 million rubles.

Overhaul of ten 35-110 kV substations, 414 transformer substations and distribution points, five 35-110 kV power transformers, 91 switches and 114 35 and 110 kV disconnectors was completed, more than 350 hectares of ROWs along power lines were cleared from trees and shrubs.

As for the large feeding centres, the 110 kV "Zhuravliki" and "Khimzavod" substations were repaired in a comprehensive manner, as well as the 35 kV "Repyakhovka", "Golovchino", "Zavidovka" substations. At the substations 110 kV "Krasnaya Yaruga" and 35 kV "Terebreno", providing power supply for about 17 thousand consumers in Krasnoyaruzhsky, in part of Rakityansky and Graivoronsky districts, the high-voltage inputs of 35 kV oil circuit breakers were replaced by modern ones with solid insulation providing a high degree of reliability of power equipment.

Over 1.1 thousand kilometres of overhead and cable lines of 0.4-110 kV were brought into the proper condition by the power company. Insulators and poles were replaced and wire and lightning protection cables were inspected at the substantial and important for several districts 110 kV overhead line "Golofeevka - Chernyanka" and 35 kV overhead line "Alekseevka - Krasnogvardeyskoye".

258.6 million rubles were allocated for the repair program of this year. The branch will perform more than 70% of the volume by own forces, which will reduce costs and allow the planned physical volume to be fully implemented.