Bryanskenergo exceeded the plan of the repair program in the first half of the year

26.07.2017

IDGC of Centre – Bryanskenergo division summed up the implementation of the repair program for six months of 2017.

The power engineers exceeded the target figures of the document. In the first half of the year, 163.3 km of overhead lines of 35-110 kV and 892.9 km of overhead lines of 0.4-10 kV (109.8% and 108.1% of the plan, respectively), 236 transformer substations of 6-10/0.4 kV (103.5% of the plan) were repaired. 373.0 hectares of ROWs of overhead lines (101.4% of the planned indicators) were cleared from tree and shrub vegetation.

In the second half of the year, the power engineers plan to repair 126.8 km of 35-110 kV overhead lines and 735.9 km of 0.4-10 kV overhead lines, 170 transformer substations of 6-10/0.4 kV, located in the service area of the branch. Comprehensive overhaul of five substations of 35-110 kV will be carried out.

The implementation of the repair program will ensure the reliability of power supply to consumers in the Bryansk region, improve the quality of electricity transmission, as well as prepare electric grid facilities of the region for the autumn-winter operation period of 2017-2018.

Other News

Back to the list