Belgorodenergo to add 19.4 MW of new capacity to housing facilities in the region

11.10.2016

IDGC of Centre - Belgorodenergo division planned to connect new 19.4 MW of electric power to develop housing facilities of the region. By the end of the year in Belgorod and districts of the region electricity will be supplied to 84 houses, including more than 35 - under housing provision programs to resettlers, orphans and children left without parental care.

Construction of power grid infrastructure is performed exactly in accordance with schedules of putting into operation. To date, grid connection has been fulfilled for 22 facilities of commercial housing and 30 - social. 43.5 million rubles were allocated to connect the last ones in the investment program of the branch.

Centralized power supply was provided to a house for orphans in the neighbourhood "East" of the regional centre, 24-apartment house in Korocha, two apartment buildings in Stary Oskol, seven houses in the village of Belovskoye in Belgorodsky district, 10 houses for displaced families and orphans in Ivnya, 7 - in Prokhorovksky district and two in the village of Bezymeno of Graivoronsky district.

In Stary Oskol, including, 28 orphans received keys to new homes in April. Two 14-apartment houses on Industrial street were supplied with electricity by the power company in the shortest possible time by constructing a package transformer substation with an overhead power line with its length of over 300 metres.

In general, in the Belgorod region to provide new homes with electricity experts have already installed more than five kilometres of overhead and cable power lines. All work has been performed with the use of modern electrical equipment, providing a high level of safety and energy efficiency.