Implementation of the repair program of Tambovenergo is on schedule

04.08.2016

IDGC of Centre - Tambovenergo division summed up the implementation of the repair program for the first half of 2016. All activities of the program are carried out in full and on time, in some cases, they are ahead of schedule.

From January to June 2016 Tambovenergo’s specialists repaired 82 transformer substations of 6-10 kV and 98 transformers of 10/0.4 kV. They repaired 352.1 km of overhead lines of 0.4-110 kV with the plan of 336.7 km. They cleared 269.1 hectares of ROWs of overhead power lines.

In total in 2016, according to the plan, the energy company will repair nearly 845.8 km of overhead lines of 0.4-110 kV, 127 transformer substations of 6-10 kV and 168 transformers of 10/0.4 kV; perform comprehensive overhaul of four substations of 35-110 kV; clear more than 469 hectares of ROWs of overhead power lines.

"All the work is done efficiently and on time. The bulk of the work must be completed before the beginning of autumn. Implementation of the planned repair program allows Tambovenergo to solve the problem of reliability of electricity supply, availability of electric grid facilities of the Tambov region for the autumn-winter operation period of 2016-2017," stressed First Deputy Director - Chief Engineer of Tambovenergo Igor Polyakov.

Other News

Back to the list