In 2016 power engineers of "Lipetskenergo" to clear nearly 461.8 hectares of ROWs along power lines

14.04.2016

In 2016, as part of the repair program IDGC of Centre - Lipetskenergo division will clear ROWs of power lines from shrub and tree seedlings along 253 overhead power lines of 0.4-110 kV with a total area of about 461.88 hectares. 15.6 million rubles will be allocated for these purposes.

Clearing will be carried out both by contractors and own forces.

The largest volume of the work will be performed on the territory of Dankovsky Distribution Zone.

Please, be reminded that clearing of ROWs of power lines allows to minimize the risk of technological failures caused by falling trees and branches on wires of overhead power lines, and thereby increase the reliability of electricity supply to customers in the region. Carrying out such work is among the priorities of IDGC of Centre.