Bryanskenergo summed up its repair program for the past year

06.03.2013

To perform the repair program in 2012, IDGC of Centre — Bryanskenergo division spent 117,768 rubles.

The program in 2012 was aimed to repair facilities, which had defects that affect the performance of equipment. In its planning letters consumers were also taken into account regarding issues of reliability of power supply.

As a result of last year 784 km of 35-110 kV overhead lines, which is 116 km more than in 2011, and 3308 km of 0.4-10 kV overhead lines were repaired. Also in 2012, 735 hectares of ROWs along overhead lines were cleared, comprehensive repair was made at six 35-110 kV substations, eight 35-110 kV power transformers were overhauled, and 690 transformer substations of 6-110 kV were repaired.

The result of this work was a significant decrease in the number of outages in power networks of the branch during the autumn-winter operation period.

The number of outages for the period from November 2012 to February 2013 decreased by 45% compared to the same period of 2011 — 2012, and the electricity not supplied decreased by 47%.