IDGC of Centre — Tambovenergo division summed up the work on grid connection for the first half of 2012. During the reporting period, the branch received 644 applications for a total capacity of 121.82 MW, 482 agreements were signed to perform grid connection of power receivers of consumers with a total capacity of 26.23 MW.
332 facilities with a total capacity of 7.12 MW were connected to the electric grid of Tambovenergo. The major customers are: LLC “Tokarevskiy Bakery”, LLC “REsource”, LLC “US-2 Interdorstroy” and LLC “Central”.
961 grid connection agreements are being executed by the branch with a total capacity of 72.2 MW.
“The largest number of applications for grid connection comes into the branch from enterprises belonging to the agricultural sector. The increased indicators of grid connection are associated with the implementation together with the administration of the Tambov region of important socio-economic and investment projects in the region. The number of requests for grid connection from Tambov residents also increases. And we make every effort so that appropriate work to be done on time and with corresponding quality”, — stressed Head of grid connection Office of IDGC of Centre — Tambovenergo division Roman Stanin.