In the first quarter of 2012 specialists of Kurskenergo performed grid connection of 425 facilities

07.06.2012

From January to March 2012 inclusive IDGC of Centre – Kurskenergo division received 484 applications for grid connection for a total capacity of 19.2 MW, including 296 applications from individuals at 3.2 MW, from legal entities - 188 applications of 16 MW.

During the period under review Kurskenergo concluded 376 contracts of 11.8 MW for a total amount of 14,790,000 rubles (without VAT).

In the first quarter of this year, 425 contracts for grid connection to the branch’s networks were executed, with 62% of applicants - individuals, the other - legal entities and individual entrepreneurs. The capacity of the connected facilities was 12.5 MW.

Among the largest facilities, connected by the branch’s specialists is ZAO NPO "Composite" (2 MW) and "Pristensky Pig Complex" (the total capacity of 1.28 MW).

Head of Grid Connection Office of IDGC of Centre - Kurskenergo division Mikhail Filipkin noted: "Kurskenergo supports its clients in all phases of applications - provides the necessary documentation, gives advice on energy supply issues, informs about changes in legislation and other processes occurring in the area of energy supply".

Requests for grid connection to the branch’s networks are submitted via Customer Service Centers and Districts of Electrical Networks. The Company also operates 8-800-50-50-115 number (toll free), with which the applicant may obtain detailed information about the list of documents required for filing an application for grid connection, learn about all the activities performed by power engineers under a grid connection contract.

Other News

Back to the list