In 2018 Tverenergo to spend over 400 million rubles to carry out the repair program

08.02.2018

To carry out the repair campaign in 2018, IDGC of Centre - Tverenergo division will spend about 439.8 million rubles. The energy company will repair about 1,333 km of overhead lines (Conductors) of 0.4-110 kV.

The list of significant energy facilities subject to repair this year includes large grid transit Conductors of 110 kV Nelidovo-Erokhino with a tap at the substation Zapadnaya Dvina, 110 kV Overhead Line Bibirevo-Ponizovye with a tap at the Substation Zapadnaya Dvina, 110 kV Overhead Line Pobeda-Chertolino, 110 kV Overhead Line Olenino-Mostovaya, and 110 kV Overhead Line CHP-3 Unit 2-Kalininskaya and 110 kV Overhead Line CHP-3-1TS-Kalininskaya , which are an important link in providing power supply to the generation facility.

In addition, separate equipment will be repaired, which at such significant substations as the 110/35/10 Substation Zapadnaya Dvina, 110/35/10 Substation Udomlya, 110/10 Substation Peno, feeding large same name settlements with socially significant facilities and developed infrastructure.

The energy company will continue paying special attention to clearing ROWs from tree and shrub vegetation. In 2018, specialists of Tverenergo plan to clear ROWs along power lines with a volume of about 2,166 hectares. Also, the branch continues implementing a long-term program to expand ROWs of 6-110 kV overhead lines. In 2018, the planned volume of expansion is 1,535 hectares.