IDGC of Centre - Bryanskenergo division summed up the implementation of the repair program for the first quarter of 2016. Implementation of measures of the document on physical volumes amounted to 121% of the approved plan. They repaired 18.8 km of overhead lines of 35-110 kV and 390.1 km of overhead lines of 0.4-10 kV (125% and 114% of the plan), 127 transformer substations of 6-10/0.4 kV (144% of the plan). They cleared ROWs along overhead lines of 0.4 - 110 kV from tree and shrub undergrowth on the area of 83.6 hectares (121% of the planned figures).
The implementation of the repair program is one of the key events to prepare electric grid facilities of Bryanskenergo for autumn-winter peak loads. Timely and full implementation of its activities allows to provide reliable power supply of consumers of the Bryansk region in the period of cold weather.