IDGC of Centre — Lipetskenergo division continues fulfilling its repair program, which provides stable operation of power equipment. All scheduled work is being done on time and in some areas ahead of schedule, in compliance with the rules and regulations on labour protection and safety.
For five months this year the following has already been refurbished: 124.5 km of overhead lines of
By the end of the year power engineer will overhaul eight substations (SS) of 35/110 kV, will perform elementwise current repair of 61 SS of 35/110 kV, and also 100 transformer substations of 10/0.4 kV, will replace 1153 poles of power lines and clear more than 210 hectares of ROWs along overhead power lines of
When performing repairs power engineers are trying to minimize the inconvenience of consumers due to power cuts. Therefore, at the time of repair customers are transferred to backup power supply circuits. Scheduled power outages are performed in accordance with pre-agreed schedules, details of which are regularly published on the website of IDGC of Centre at www.mrsk-1.ru.