In 2011 Bryanskenergo signed nearly a thousand contracts on technological connection

14.02.2012

IDGC of Centre — Bryanskenergo division summed up the work on technological connection of consumers to the grid of the branch in 2011.

Last year, Bryanskenergo signed 993 contracts on technological connection with electric power consumers that is 138 contracts more than in 2010. The increase in the number of contracts is due to the reduction of fee for technological connection to electric networks for legal persons, as well as the application of preferential tariff for the technological connection of up to 15 kW.

Last year residential consumers contacted Bryanskenergo more often than legal entities. They signed 530 contracts and legal entities 463 contracts.

The total capacity of the connected facilities for the year was 13.35 MW. In 2011 some social facilities (kindergartens, schools and others) with a total capacity of 1.25 MW were connected to the Bryanskenergo grid. The largest connected sites in the past year were LLC Bryansk Meat Company, the customs terminals in Pogar and Klimovo and others.

According to the chief of Bryanskenergo Department on work with clients of technological connections Victor Kurylenko, the branch takes all necessary steps to provide its clients with high quality technological connection as soon as possible. The work of Bryanskenergo staff is focused on creation of the most convenient and cost-effective conditions for customers to implement the technological connection to the grid of the division.